________________________________ 
 
    Introduction
 
    
Symbols and Keywords
 
 I.       BUILDING STRUCTURES
     A.    Introduction

    B.    Intro to Seismic Upgrading

    C.    Structural Concepts  

        C1. Technical Commentary (1)

        C2. Technical Commentary (2)

    D.    Step 1: Risk Assessment

        D1. Upgrade Priority

        D2. Geographical Risk

        D3. Building Structural Types

        D4. Year of Construction

        D5. Load-path Assets+Debits

        D6. Rapid Visual Survey Sheet
     E.    Step 2: Mitigation Measures

 

II.      UTILITY SYSTEMS

    A.     Introduction

    B.     Utility Mitigation Measures

 

 Appendices
     A.      Regulations
     B.      Glossary

     C.      Acronyms
     D.      References
     E.      List of Contributors

Install Tension Ties Between Elements

During an earthquake, many unreinforced masonry and wood buildings suffer damage or even collapse due to inadequate connections between the walls and the roof/floor systems. Tying the walls to the roof and floor systems using tension ties can strengthen these buildings. Tension ties limit wall deflections by tying them to the floor system, thereby reducing the likelihood of damage or building failure. 

Effectiveness:

  • Very effective.
  • Consider adding shear anchors to the walls to increase effectiveness.

 

 

NOTE:  None of the mitigation measures in these Handbooks should be considered ‘pre-approved’ or otherwise automatically eligible for FEMA funding. Only FEMA staff can determine eligibility, once they have determined that an applicant is eligible and they have reviewed a project proposal.

FEMA HAZARD MITIGATION HANDBOOKS                                                                        Updated: June 13, 2002